Project Synchronization

Started by pylb, December 15, 2018, 09:01:14 AM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

pylb

Hi all,

With Visio 2016 (not 356),

I try to synch a 2016 Project with Visio 2016.

I can create a new diagram but can't update an existing when I've modify Project.

Is it possible?


Thanks in advance

AJD

QuoteIs it possible?

Of course it is. How much time and effort do you want to expend on this?
- Which application/file is managing the synchronisation (e.g. is it triggered by a change in Project or a by a change in Visio)?
- What data are you synchronising?
- How can you tell if a re-synch is required?
- How is your data linked to your diagram?
- Are you synchronising through a data set or through VBA?

And those questions above are only the start in order to help answer your immediate question.